September 2006 - Duferco Farrell Corp., Farrell, Pa., is dedicated to satisfying its customers' every need when it comes to providing manufacturers and service centers with steel. Offerings include low-carbon, high-carbon, high-strength low-alloy and alloy steel. It can also accommodate special needs such as restrictive gauge tolerance, flatness, or chemical and physical properties.
Minimum order quantity is the product of one slab, approximately 40,000 pounds, considerably smaller than the industry heat lot minimum.
To meet the increasing demands seen at the Farrell plant since Duferco acquired it in 1999, the company invests in a continuous stream of new equipment and upgrades. Since the acquisition, it has spent more than $50 million to improve productivity.
The heavy investment is paying off because the total capacity of the facility has grown to 2 million tons per year. Individual unit capacities include the tandem mill with 900,000 tons per year, temper rolling with 700,000 tons per year and annealing with 400,000 tons per year. Annually, the No. 7 pickle line processes one million tons of steel in thicknesses from 0.060 inches through 0.187 inches and in widths from 29 inches to 56 inches.
Scott Bishop, general manager of cold rolling at Duferco Farrell says the No. 7 pickle line created a bottleneck, so the company designated it for improvement. The first pickle line upgrade was completed in 2004 when Duferco Farrell partnered with Butech-Bliss, Salem, Ohio, to implement an exit-end rebuild.
A replacement strip notcher along with automated steering roller side guide, a turret edge trimmer and double-hub scrap choppers were installed. The upgrade brought line capacity from 550,000 tons per year to 700,000 tons per year.
While this was a good start, a new minimum goal of 900,000 tons per year prompted the company to look at the next option--a second pay-off reel.
Big results, small downtime
Wesley Zipay, Duferco Farrell's plant mechanical engineer, worked closely with Butech-Bliss to design and engineer a second upgrade for the line's entry end. The two companies again joined efforts to coordinate installation preparatory work, prepare foundations and modify existing equipment with minimal downtime.
Upgrades focused not only on maximizing each piece of equipment but also on building in ease of maintenance for continued productivity following project completion.
"We not only looked at the function of the equipment, we looked at accessibility for maintenance and operations so the equipment wasn't just there for the function. We could maintain it and get user-friendly with it," says Zipay.
Timing for installation of each element of the upgrade was studied, resulting in a large percentage of installations and modifications being accomplished during scheduled line maintenance.
"We were able to set the major portions of the equipment during the operations. It was choreographed so that when the equipment came in, it was able to go off the trucks and onto the foundations," Zipay continues.
"The only way we could pull this off was to do most of the work during repair turns. A lot of the preparatory work was done while the line was running," says Bishop. Actual downtime for the final merging of the two systems was seven days.
New mechanics, new software
Butech-Bliss furnished an additional entry end for the continuous pickle line that included coil storage and handling equipment to complement the existing line that was running around-the-clock. The new second strip passline runs above the existing entry equipment.
New equipment includes a five-station coil storage conveyor, coil loading car, auto-positioning uncoiler, coil snubber, five-roll flattener with entry pinch rolls, hydraulic shear and scrap conveyor, strip thread tables, steering pinch rolls and a hole punch.
A newly developed Butech vision control system is critical to the operation. One task of the vision system is automated coil loading. A coil is loaded from the coil storage conveyor onto the floor-mounted coil loading car and then moves to the positioning uncoiler where the vision system keeps strip on center during the line run.
The vision system also provides strip width information for both pass lines and steers strip during threading and line run using the steering pinch rolls. Video cameras command actuators on the pinch rolls through closed loop control software.
A strip hole punch unit was mounted after the stitcher. The stitch is tracked through the process line for subsequent removal using the punched hole. New hydraulic power units, valves and sensors were also furnished. One power unit was needed for the new entry equipment, and the other helped reduce coil-joining time at the stitcher.
Four minutes to 50 seconds
Prior to Duferco Farrell's 60-inch continuous pickle line entry-end upgrade, the company spent an average of four minutes joining the two coils for the continuous process. Steps entailed trimming the tail end, feeding the next coil into the processor, cutting the scrap off the head end, moving the coils into the stitcher and joining the coils. Cycle time dropped to 50 seconds following the upgrade.
Three improvements contribute to the dramatic time savings, according to Bishop. First, having the second entry pass line located 15 feet ahead of the stitcher positions the next coil for automatic loading.
Second, the speed of the stitcher process was increased. Previous cycle time to make a stitch was 45 seconds. Combination of the new stitcher hydraulic system, control modifications and flattening clamp assembly cut the stitching cycle time down to 24 seconds, a reduction of nearly half.
The third improvement allows the company to save time when aligning the strip. Prior to the upgrade, aligning the tail and head of the coil was a manual process. The operator used side guides at the entry and end of the stitcher to correctly position the coil ends. Bishop says that process typically took about half of the four-minute cycle time.
Vision system cameras located at each of the four steering pinch rolls monitor the head and tail, identify their position and command the pinch rolls to correct for offset and potential skew (nonparallelism). The pinch rolls are mounted on sub-bases and are actuated via hydraulic cylinders and proportional valves.
Once the system reads the correct position, it sends a signal and the stitch cycle begins. "We used to take between a minute and two minutes to align the strips," says Bishop. "This system has made that more of a 10-second operation." He calls this "the best part of the whole upgrade."
Improvements continue to pay off
The goal of a 900,000-ton capacity for Duferco Farrell's pickle line has been achieved and surpassed.
"This upgrade has taken us to a whole new level of business. Because of our pickle-line capacity we were limited to about 60,000 cold-roll tons per month," Bishop says. "Now we are consistently at 80,000 tons per month going through our cold mill. It has allowed us to reach our capacity levels in the cold-mill side." He notes that Duferco Farrell is doing better than ever, without an end in sight. Upgrades on the tandem mill and temper mills are scheduled for later this year. MM
By Sue Roberts, from the September 2006 issue of Modern Metals.